Question7 0.2 pts The project manager asked you to evaluate the project performance at the end of year 1 by using performance indexes. He gave you the following information: actual cost is $307380, earned value is $319039, and planned value is $315910. Calculate the cost performance index(CPI) of this project at year 1 Enter your answer as: 1.23 Round your answer to 2 decimal places Show transcribed image text
Question7 0.2 pts The project manager asked you to evaluate the project performance at the end of year 1 by using performance indexes. He gave you the following information: actual cost is $307380, earned value is $319039, and planned value is $315910. Calculate the cost performance index(CPI) of this project at year 1 Enter your answer as: 1.23 Round your answer to 2 decimal places